Saturday, April 25, 2015

EMP COMPLETES INSTALLATION AND TESTING AT SITE

                                          After testing EMP Wet Process line

                                                             Dry line tested

EMP Press and Sartorius Metal Detector Tested

Mr Kang and our electrical supervisor successfully tested all our EMP Skim block line yesterday. We are satisfied with the performance of the Wet Process line and dry line though they were tested without rubber.

The client will begin to test our line with rubber soon. We intend to visit the factory again in 3 months time.

Thursday, April 23, 2015

TESTING EMP SKIM BLOCK PROCESSING LINE AT FACTORY SITE

Testing EMP Hybrid Dryer

Wet line being tested

Our company is currently testing our EMP Skim block processing system in Thailand. All the machinery, hybrid dryer, press and metal detector are functioning according to our designed parameters.

Tuesday, April 7, 2015

EMP COMPLETES M & E INSTALLATION AT SITE

Finally after 3 months delay, our Wet Process line for our EMP Skim Block line is completed. The line was installed after the concrete plinth was completed. Now, the line has been wired up and is ready for final checking and testing. This will be done after the Songkran holidays next week.

EMP Skim Block Wet Line Ready for Testing

Remote Control Panel for the Wet Line

Sunday, April 5, 2015

WIRING UP EMP WET PROCESSING LINE OF SKIM BLOCK PLANT



We are doing the wiring of our EMP wet processing line of our skim block  processing line in Thailand.

Once it is completed, we will be sending our electrical supervisor to test the wet line and dry line of the skim block line.