Our turnkey Skim Block rubber processing system is now at the site installation stage. All the machinery and equipment were safely delivered to factory site on 22nd. November 2014. Our Managing Director, flew in and visited the factory to inspect the machinery and equipment. All the equipment were checked and verified by the owners as well. By shipping out the machinery and equipment in 5nos. x 40ft. containers proved invaluable as all items were delivered intact and no pilferage were discovered.
Our project is in the site installation stage. Thai contractors and some minor material will be bought to complete the installation of the dryer. With our