Saturday, December 27, 2014

MECHANICAL INSTALLATION OF EMP DRYER DONE

Major installation works of our dryer has been completed at site in Surat.

Thursday, December 18, 2014

MR KANG LEAVING SURAT TO THUNG SONG TODAY

Our Managing director after supervising dryer installation at site for past 4 days will leave Surat and travel to Thung Song today. Hope to meet up with a buyer for a potential rubber project in S. Thailand. On Saturday, he will visit our dryer installed 6 months ago. We want to get feedback from our customer about our dryer performance. ago

EMP INSTALLATION TEAM AT SITE IN S. THAILAND

Wednesday, November 26, 2014

SITE INSTALLATION STAGE OF TURNKEY PROJECT IN THAILAND

Our turnkey Skim Block rubber processing system is now at the site installation stage. All the machinery and equipment were safely delivered to factory site on 22nd. November 2014. Our Managing Director, flew in and visited the factory to inspect the machinery and equipment. All the equipment were checked and verified by the owners as well. By shipping out the machinery and equipment in 5nos. x 40ft. containers proved invaluable as all items were delivered intact and no pilferage were discovered.

Our project is in the site installation stage. Thai contractors and some minor material will be bought to complete the installation of the dryer. With our

Monday, November 24, 2014

INSPECTION OF MACHINERY AT FACTORY AND MACHINERY LAYOUT

EMP Final Shredder on frame with Stainless Steel Trough at the bottom.
Battery of EMP Crepers in line formation
EMP Dryer being installed.

Saturday, November 22, 2014

OUR 5 X 40FT. CONTAINERS ARRIVED AT THAI FACTORY YESTERDAY

Our EMP Skim Block Rubber processing system shipped out in 5 x 40ft. containers has arrived at our customer's factory yesterday after clearing Thai Customs on 21st.November 2014.

Mr. Kang, our Managing Director will be flying into Southern Thailand tomorrow to oversee the machinery layout at site and start off the installation of mechanical and electrical works by our Thai contractors. Some items will be purchased in Thailand for the insulation of the dryer at site.

We hope to complete the installation works by mid December 2014 so that the final inspection and energising of the line can be done.

Thursday, November 13, 2014

LOADING OF LAST CONTAINER COMPLETED

Our last machinery and equipment for our EMP Skim block lone were finally loaded this afternoon.Over a period of 3 days, we loaded our machinery and equipment. Rain damping slightly our loading works but we overcome that. The last machinery that was put into the final container was our EMP 60 tonnes press.

Tuesday, November 11, 2014

LOADING OF EMP SKIM BLOCK SYSTEM HAS BEGUN

We started loading our completed Skim block system yesterday. We had to load some equipment at night. Luckily, with high beam light using my car. Another two more containers will be loaded today.

Monday, November 10, 2014

ALL GOODS READY TO BE LOADED INTO CONTAINERS

All our goods are ready to be loaded today. 2 x 40ft containers are coming today for loading. Our EMP 60 tons press panel has been shrinked wrap against water and we have also shrinked wrapped the hydraulic package.

CRATING OF ELECTRIC PANELS AND METAL DETECTORS

In our final phase of our turnkey project by packing our sensitive items such electrical panels and the Sartorius metal detector. In our final phase

Friday, November 7, 2014

EMP 60TONS MOVING CHAMBER PRESS TESTED AND READY FOR DELIVERY

Tested EMP 60 tons press is ready for delivery. All safety guards are painted bright yellow so that users are aware of danger zones. The guards are mounted to prevent accidents from occurring.

Tuesday, November 4, 2014

TESTING EMP PRESS BEFORE DELIVERY

All our machinery are factory tested before delivery. Photo shows our press being wired up before testing the controls and operation.

Saturday, November 1, 2014

EMP MOVING CHAMBER PRESS WIRED UP FOR TESTING

Our EMP Press has been wired up before testing next week. Powered by German made dual pump and auxillary hydraulic items, our press is reliable and robust.

Wednesday, October 29, 2014

EMP TURNKEY SKIM BLOCK PROJECT ENTERS DELIVERY STAGE

Within the next 2 weeks, all our skim block wet and dry process will be trucked up Surat Thani, Southern Thailand. Crate measurements have already been measured and inter country trucking company has been engaged. We estimate that 5 nos. of 40 ft containers will be needed to deliver all our goods. Some finishing works need to be done and the press tested before all the machinery be painted. Sensitive machinery and electrical starter panels will be crated to prevent damage against mishandling and rain.

Tuesday, October 28, 2014

DRYER STRUCTURES AND TROLLIES READY FOR SHIPMENT

The dryer structures are being mounted with stainless steel sheets. The dryer trollies have been completed. Once all items are ready, we will truck all the machinery and equipment to Thailand.

Saturday, October 25, 2014

EMP WET PANEL AND DRYER PANEL BEING MADE

As our delivery schedule draws near, our wet process and dryer panels are being made.

Thursday, October 23, 2014

EMP PRESS READY TO BE WIRED UP FOR TEST RUN

Our EMP 60tons moving chamber press is to be wired up for testing. After testing, it will be painted before delivery.

Monday, October 20, 2014

SPARE HELICAL GEARBOX ARRIVES

As part of our turnkey project, we are supplying a spare helical gearbox as a spare for their crepers. The client can quickly change the gearbox if any of the creper gearbox malfunction.

Monday, October 13, 2014

SARTORIUS METAL DETECTOR READY TO BE PACKED

<+60 16-384 8550div
class="separator" style="clear: both; text-align: center;">

EMP DRYER MAIN FAN IN PLACE WITH DRYER MIMIC DIAGRAM

TAPPING ACCESSORIES READY FOR SHIPMENT TO AFRICA

Our tapping accessories are ready for shipment to Africa. This order is placed by our long standing African client.

Goods have been packed and will be delivered to our stores for shipment.

Tuesday, October 7, 2014

EMP STATIC CRUSHER COMPLETED

Our initial size reduction crusher has been completed. It will be used to reduce coagulated slabs into 1" thick slabs before they are further processed.

Monday, October 6, 2014

EMP 60 tonnes Moving Chamber Press Being fabricated

Besides the EMP Skim block dryer being constructed, we are also fabricating our 60 tonnes moving chamber press. The press structure is being done including the double chamber.

Thursday, October 2, 2014

DRYER MAIN CIRCULATION FAN DELIVERED FOR DRYER FABRICATION

Dryer being fabricated. Main circulation has been delivered so that it can be mounted. Exhaust and cooling fans will also be delivered soon.

Wednesday, September 24, 2014

EMP STATIC CRUSHER TAKING SHAPE

EMP Static Crusher

Our EMP Static Crusher for reducing skim blocks into slabs of 1" thickness is fast being fabricated. Our manufacturer only needs to install the gearboxes and the motor. The prime mover will be used to power the two rollers.

Once all the components are installed, the crusher will be ready to be delivered to our Thai client.

Crushers can be used to reduce large rubber slabs into thinner slabs and dewater the rubber. They can be used as the primary pre-size reduction machine such as crushing embedded stones in the rubber slab and take out unwanted water as well.

If interested, please email us at TWKANG@emp.com.my

Tuesday, September 23, 2014

EMP TRADING DIVISION SECURES TAPPING ACCESSORIES ORDER

Our African client has confirmed their order for the supply of Ethephon Plus latex stimulants, Gebung type rubber tapping knives, Upward cut tapping knives and sharpening stones.

Our company will be expediting the order from our long term client in Africa. This plantation group has been our customer for the past 20 years and we value their continuous support in ordering our products.

Plantation companies interested in our products can always email us at TWKANG@emp.com.my

EMP Skim Block Wet Process Line Electrical Panel being manufactured

All our EMP Wet Process line for skim block production are being painted before delivery. Our company is now fabricating the Process line Electrical Panel. Our mimic diagram is ready to be mounted onto the electrical panel before it is tested.

Once tested, the panel will be wrapped in plastic and crated before delivery.

Monday, September 8, 2014

Our EMP Wet Processing line is being painted before delivery to our Thai client. They came to inspect the machinery recently and decided on the colours. Bright colour to be painted on all guards while metallic blue for machinery against acidic environment.

Sunday, August 31, 2014

EMP WET SKIM BLOCK LINE

Preparing our EMP Wet line processing system for end September delivery. Colour code for the machinery has been approved by the buyer who came in on 30.8.2014 to inspect the machinery.

We will be painting the completed machinery with the agreed colour codes before itemising them for partial delivery of the wet process line.

All our machinery and auxilliary items are pre-marked at the factory site before delivery. Mechanical installation is simplified and no civil works such as foundations are required. The crusher, crepers, belt conveyors and shredder are designed for easy installation and alignment. Only a flat concrete factory floor is required. Mechanical installation at site can be done within a day or two - thus saving time.

Wednesday, August 13, 2014

EMP MALAYSIA TO QUOTE TSR 20 LINE TO THAILAND

Our Projects and Engineering Division has submitted our proposal to this potential Thai client for our EMP 2mt/hr TSR 20 Automatic Rubber processing line recently. We are awaiting for their feedback on our proposal. Interested parties interested in our TSR rubber processing lines can always contact us at : TWKANG@emp.com.my

Tuesday, August 12, 2014

EMP FAN DIVISION SUBMITS COWDRAY FANS FOR OIL PALM MILL IN INDONESIA

Our Fan Division has submitted a quotation for 8 sets of Cowdray centrifugal fans to Indonesia. We have an authorized agent for our Cowdray fans for oil palm mills in Indonesia. Last year we exported our Cowdray fans through this agent. We hope to get this order as well.

Friday, August 8, 2014

EMP MALAYSIA ASSEMBLES SKIM BLOCK WET PROCESS LINE FOR THAI CLIENT

EMP Crepers being assembled Our EMP Skim block process line is being assembled. Comprising of a static crusher, 3 crepers and a final size reduction shredder and belt conveyors, they can be ready for inspection by our Thai client by mid September. We will decide the colour scheme as well after the inspection.